865 WorkRate |
Name : _________________ |
||
If Ann does a job in 8 days, and Bob does it in 10 days, how long do they take together? (Nearest to the 10th...) |
If Ann does a job in 8 days, and Bob does it in 10 days, how long do they take together? (Nearest to the 10th...) |
+( ) |
|
( )+ |
++[[ ]]++ |
||
865 4.4 1.7 2.5 3.2 2.2 ( 14 ) 4.4 1.9 2.9 3.5 3.3 ( 16 ) [[ 30 ]] | ||
|