310 WorkRate |
Name : _________________ |
||
If Ann does a job in 3 days, and Bob does it in 4 days, how long do they take together? (Nearest to the 10th...) |
If Ann does a job in 6 days, and Bob does it in 5 days, how long do they take together? (Nearest to the 10th...) |
+( ) |
|
( )+ |
++[[ ]]++ |
||
310 1.7 2.2 4.4 1.9 1.2 ( 11.4 ) 2.7 3.6 1.6 1.7 3.2 ( 12.8 ) [[ 24.2 ]] | ||
|