996 WorkRate |
Name : _________________ |
||
If Ann does a job in 10 days, and Bob does it in 4 days, how long do they take together? (Nearest to the 10th...) |
If Ann does a job in 4 days, and Bob does it in 7 days, how long do they take together? (Nearest to the 10th...) |
+( ) |
|
( )+ |
++[[ ]]++ |
||
996 2.9 1.6 3.9 1.3 2.8 ( 12.5 ) 2.5 2.3 1.6 2.2 3 ( 11.6 ) [[ 24.1 ]] | ||
|